copper pipe schedules

Home Forums Public Forums General Plumbing copper pipe schedules

Viewing 5 reply threads
  • Author
    Posts
    • #277193
      Robert La Bianca

      I’m going to run new supply and sanitary lines under a slab. What schedule of copper do I use for the supply and what schedule pvc for the drain (this will be for a slop sink and washing machine) the run will be about 30 ft. how much pitch do I need for the drain?

    • #295677
      Retired plbg1

      Use Sch. 40 pvc for drain lines, use type K soft copper underground and loop it back and forth so you do not have any joints under slab, if you have joints use hard solder like silfuss.



      Art retired plbg

    • #295678
      Retired plbg1

      I forgot when you come through con. Floor put armor flex pipe insulation on pipe comming out of slab before they poor con.



      Art retired plbg

    • #295679
      larryw

      Thanks, R.P. not quite sure what you mean by looping back and forth though. Also what pitch should the drain line be?
      Larry

    • #295680
      Retired plbg1

      Pitch can be 1/8″ per ft. of pipe + or – usualy about 1″ per 10 ft. of pipe, if you are deep you can give it a 1/4″ per. ft. What I meant about looping pipe is like say you are running pipe to sink straight ahead and there is a Lav. before you get to sink well instead of putting a tee in line and run pipe to lav. you run a seperate pipe to lav and sink. Say you had 3 fix. to run cw too, well where your source is you start and run 1 line to each fix an connect the 3 lines and then connect to the source. If you send me your e-mail add. i will draw it up for you.



      Art retired plbg

    • #295681
      larryw

      Thanks again, no need to draw it up.
      Larry